Custom residential build near Albuquerque. Flowverge is tracking preconstruction decisions, long-lead materials, supplier reliability and make-ready constraints before the first crew is blocked.
Target cycle6 months
Current market assumption: 6-8 months
Command Center
Portfolio health
Ready to build68%
Sandia Residence
Start risk14 days
Driven by windows and cabinets
Open decisions7
5 affect schedule
Recoverable time21 days
Across selections and procurement
Active projects
AI prioritized
ProjectReadyRiskNext action
Days at risk
Hidden AI insight
Windows lead time conflictSupplier A is cheaper but pushes framing enclosure.
12d
Cabinet package unresolvedClient has 4 options without schedule impact shown.
9d
Permit package missing sheetStructural S2.1 not attached to submission set.
?
Project Readiness
Can this project start cleanly?
68%ready
Start risk:14 days
Flowverge found three constraints that can delay the real start even if the schedule says the project is ready.
Blocking decisions
Recommended order
Windows package
Approve supplier with 4 week lead time to avoid enclosure delay.
12d impact
Cabinet package
Client needs one curated recommendation, not four open options.
9d impact
Permit set
Attach structural sheet S2.1 before submission follow-up.
Owner
Readiness checklist
Should | Can | Will
Scope locked
Budget target set
Materials 62%
Long-lead items 48%
Subcontractor shortlist
Permit package incomplete
Material Selection Studio
Close decisions without slowing the build
Package A
Budget Control
Lowest upfront price, but longer cabinet and window lead times.
Cost
$24,180
Lead time
7 weeks
Schedule risk
High
Recommended
Package B
Schedule Saver
Balanced selections with local availability and faster enclosure path.
Cost
$25,420
Lead time
3 weeks
Schedule risk
Low
Package C
Premium Finish
Higher finish level with custom order exposure and price variance.
Cost
$31,880
Lead time
6 weeks
Schedule risk
Medium
Decision impact
Approving Package B recovers 11 calendar days.
Flowverge recommends the package with the best cost of schedule, not the lowest sticker price.
Procurement
Compare suppliers by cost of delay
Windows RFQ
3 quotes normalized
SupplierPriceLead timeReliabilityDecision
ABC Supply$18,9008 weeks73%Reject
Desert Build Co.$20,1004 weeks91%Use
Rio Materials$19,6006 weeks82%Backup
PO draft
Pending approval
VendorDesert Build Co.
ItemWindow package B
Expected deliveryAug 12
Schedule effect11 days recovered
Why not the cheapest?
The cheaper quote risks 12 days of idle schedule.
A $1,200 price difference is smaller than the operational cost of a delayed enclosure path.